Schedule of Outages:Â 28th March - 4th April 2009
|
Date |
Work to be Carried Out |
Proposed Commencement of Work |
Duration of Work |
Area Affected |
| Sunday 29th | Rearranging Circuit Route |
08:30 Hrs |
8 Hours |
Section K Campbellville to Hadfield Street Part of Bel Air Park & Homestretch Avenue; |
| Monday 30th | Changing primary poles & transferring line hardware to new poles |
08:30 Hrs |
4Â Hours | Eccles & Bagotstown |
| Tuesday 31st | Changing primary poles & transferring line hardware to new poles |
08:30 Hrs |
8 Hours |
Sandy Babb & Middleton Streets; Railway Line to Stanley Place & David Streets |
| Wednesday 1st | Changing primary poles & transferring line hardware to new poles |
08:30 Hrs |
8 Hours | Sophia to Bygeval |
| Thursday 2nd |
Installing pole span of wire; Changing primary poles & transferring line hardware to new poles |
08:30 Hrs |
8 Hours | Lamaha Gardens, Prashad Nagar, Campbellville; Section K to Hadfield Street Lodge |
| Thursday 2nd | Changing primary poles & transferring line hardware to new poles |
08:30 Hrs |
8 Hours | GOE to Hope |